Equinix stock: Dallas data-center filing meets fresh quote
Published on 11/20/2026 at 16:56 | Editorial responsibility: Rafael Müller, Editor-in-Chief AD HOC NEWSDallas capacity plans meet fresh market focus
- An Equinix affiliate filed plans for the DA13 data center near Dallas Love Field.
- Construction is scheduled from February 2027 through December 2029.
- The project remains a preliminary filing rather than a completed investment.
Equinix stock traded at 910.40 euros on Lang & Schwarz at 16:40 CET on Friday, November 20. The gap to the 946.30 euros quoted at 16:01 CET on Thursday, November 19, was 3.79 percent.
Dallas project expands planned capacity
The Dallas Morning News reported on November 13 that an Equinix affiliate had filed plans for the DA13 data center near Love Field. The filing covers a four-story facility at 1520 W. Mockingbird Lane with an estimated construction cost of 500 million US dollars.
The project is registered to DA12 LLC, whose address is the same as Equinix's Redwood City headquarters. The Dallas Morning News reported that Equinix plans capacity for about 3,700 cabinets and 62.5 megawatts.
Project timing remains preliminary
Construction is scheduled to begin in February 2027 and finish in December 2029. The filing lists 18 generators, but project specifications and costs can change as the permitting process develops.
For investors, DA13 would extend Equinix's Dallas-Fort Worth footprint and add planned capacity for data center customers. The filing is a development plan, not evidence that the facility is already operating or that the full investment has been made.
Equinix company facts
- Company: Equinix Inc.
- ISIN: US29444U7000
- Quoted price: 910.40 euros
- Trading venue: Lang & Schwarz
- Quote time: 16:40 CET, Friday, November 20, 2026
US equities remain in focus in Current market reports.